Concrete slab calculator
A 10 × 10 ft slab 4 in thick needs 1.23 cubic yards of concrete, or 1.36 yards with 10% extra: 62 bags of 80 lb mix or 82 bags of 60 lb. Enter your slab's size for your own numbers.
Measuring the slab
Measure the inside of the forms, not the outside, and take the thickness from the top of the form to the prepared base in a few places. Ground is rarely flat: if one corner is half an inch lower than you thought, that corner takes more concrete. The National Ready Mixed Concrete Association gives the example of a 4 in slab that ends up 1/8 in thicker than planned, which is a 3 percent shortfall, and advises ordering at least 4 to 10 percent more than the measured volume. The calculator adds 10% unless you choose otherwise.
For an L-shaped patio, split it into two rectangles and add the results. For a round slab, use the column calculator with the slab's diameter and its thickness as the height.
Worked example: a 12 × 20 ft driveway pad, 5 in thick
12 ft × 20 ft × 5 in = 100 cu ft
100 cu ft ÷ 27 = 3.70 cu yd
With 10% extra: 4.07 cu yd, or 184 bags of 80 lb mix
At that size, ready-mix is the sensible choice: the calculator rounds the order up to 4.25 cubic yards.
Common slab sizes at 4 in thick
| Slab | Cu yd (exact) | Cu yd with 10% | 80 lb bags | 60 lb bags |
|---|---|---|---|---|
| 4 × 4 ft | 0.20 | 0.22 | 10 | 14 |
| 4 × 8 ft | 0.40 | 0.43 | 20 | 27 |
| 6 × 6 ft | 0.44 | 0.49 | 22 | 30 |
| 8 × 8 ft | 0.79 | 0.87 | 40 | 53 |
| 8 × 10 ft | 0.99 | 1.09 | 49 | 66 |
| 10 × 10 ft | 1.23 | 1.36 | 62 | 82 |
| 10 × 12 ft | 1.48 | 1.63 | 74 | 98 |
| 10 × 20 ft | 2.47 | 2.72 | 123 | 163 |
| 12 × 12 ft | 1.78 | 1.96 | 88 | 118 |
| 12 × 20 ft | 2.96 | 3.26 | 147 | 196 |
| 16 × 16 ft | 3.16 | 3.48 | 157 | 209 |
| 20 × 20 ft | 4.94 | 5.43 | 245 | 326 |
| 20 × 24 ft | 5.93 | 6.52 | 294 | 392 |
| 24 × 24 ft | 7.11 | 7.82 | 352 | 470 |
| 30 × 30 ft | 11.11 | 12.22 | 550 | 734 |
Concrete per square foot
Each inch of thickness adds 1/12 cu ft for every square foot of slab. One cubic yard covers 324 sq ft at 1 in, so divide 324 by the thickness in inches to see how far a yard goes.
| Thickness | Cu ft per sq ft | Sq ft per cu yd | 80 lb bags per 100 sq ft |
|---|---|---|---|
| 3.5 in | 0.292 | 92.6 | 49 |
| 4 in | 0.333 | 81 | 56 |
| 5 in | 0.417 | 64.8 | 70 |
| 6 in | 0.5 | 54 | 84 |
| 8 in | 0.667 | 40.5 | 112 |
How thick to pour
The International Residential Code asks for concrete floor slabs at least 3½ in thick. Patios, walks and shed bases are commonly 4 in. Driveways and slabs that carry heavy vehicles or equipment are usually poured thicker, and many towns set their own minimum for driveways, so check with your building department before you order. A thicker slab also needs a well compacted base under it; the crushed stone calculator works out the gravel for that layer.
Sources
- CIP 8: Discrepancies in Yield (Concrete in Practice series), National Ready Mixed Concrete Association, 2016 edition. Order at least 4 to 10 percent more than the measured volume; 1/8 in extra on a 4 in slab is a 3 percent shortfall.
- International Residential Code, sections R403.1.1 and R506.1, International Code Council, 2021 edition. Spread footings at least 6 in thick with projections of 2 in or more; Table R403.1 widths start at 12 in; concrete floor slabs at least 3.5 in thick.
- QUIKRETE Concrete Mix (No. 1101) data sheet, The QUIKRETE Companies, revised October 2022. Bag yields: 40 lb 0.30 cu ft, 50 lb 0.375, 60 lb 0.45, 80 lb 0.60, 90 lb 0.675; about 140 lb per cubic foot.